I collated this list via much reading on Home One forum and from friends. Some things are repeated and simply not possible with PD but at least this list might help someone else thinking of building.
Site works and administration:
·
Want Copy of site
survey & soil test. Check elevations.
·
Make sure
contract reflects that the start date is the date that work commences onsite.
·
Check that
contract only allows for rainy days being claimed before roofing is installed
and only if there has been more than 5mm of rain.
·
Independent
Inspector & PD response to correct issues found
·
Confirm setback
from street 9m or can we apply for less? Current carport 4m, house 9m.
·
When will
application be submitted to Glen Eira Council?
·
Start date issue
House:
·
Correct
orientation of house, garage on correct side.
·
Upgrade carpet
underlay, blue
·
Check location of
windows is exactly where you want on final plan before signing off.
·
Check all windows
are the same (awning) and from the same manufacturer so you don’t have two sets
of keys
·
Check window
position, are they in the center of the rooms
·
Think about
location of water tanks,
·
Ensure insulation
is installed correctly......... between floors. Sound battens
·
Check extended
eaves
·
Check double
glazing for windows
·
Check location of
manhole, in relation to ducted heating if it is too close to all the big ducts
then you can’t access any other part of the roof space
·
"Whirly
Bird" or other roof ventilator(s) .
Structural:
·
Be aware of the
INTERNAL dimensions of your garage.
·
Insist on a
three-coat paint job (1 * sealer, 2 * top coats) / Use a premium paint product
for a longer-lasting finish WASH & WEAR
·
Install extra
noggings / studs / trimmers for mounting heavy pictures, TV's, projectors,
screens, curtain tracks/blinds/school bags / jackets / dog leads in laundry /
hall / cupboards understairs/ hang on walls, pictures, televisions, speakers,
coat hooks, clothes dryer, toilet paper, towel rails, in hall cloak room,
future shelves need noggins/ ceiling fan electrical provision and nogging in
bedrooms and outdoor entertaining area (alfresco / gazebo)
·
Check position of
power meterbox & which side
·
Check position of
hot water, evaporative cooling, water tank, pool equipment, Will you be able
move wheelbarrow past this section of house.
·
translucent (no
see through) glass on the front door side panel.
·
Acoustic batt
insulation - dense/heavier, between floors, all walls.
·
Termite Barriers
are they included?
·
Retro FaƧade
& FULL hebel to house (clarify if any areas not hebeled)
·
FaƧade tiling was
quoted at $150/m is this correct. MAXFL1740 tile to pillar and render area on
faƧade (?20sqm)
Doors
·
Check rail for
flyscreen doors added to backdoors (A&L range)
·
Check theatre
sliding door type. Cavity sliding door.
·
Door heights
increase with higher ceilings and noted on contract (upstairs too)
·
Locks are
keyed-alike so you don’t end up with multiple keys to lock up doors/windows.
·
Are door stops
included and installed?
·
secure internal
door from garage into house instead of light non lockable standard door
·
Rebating external
sliding doors so that the door sill is flush with the concrete slab
·
Electrical/Lighting
·
Zoned lighting,
controls for Shabbat, load spreading.
·
3 phase power pit
organised
·
Install
electrical conduit to provide 12 volt electricity for garden lighting
·
Install household
surge protector at meter
·
Circuit for pool
equipment
·
Digital TV Aerial
·
Front door,
confirm window next to it on one or both sides of door.
·
Bulkheads for
kitchen cabinet doors and wardrobes in bedroom
Plumbing:
·
Rain water tanks -
plumbing for washing machine / laundry / toilets (auto flickover to Water
supply), garden
·
Move laundry taps
so easily accessible
·
Check downpipe
locations
·
Waste points in floor
in laundry, bathrooms. Check locations.
·
Check the
location of your HWS, outdoor taps, Hot/cold shower outdoor, pool
·
HWS is seated on
a concrete footing (or slab) rather than on top of the ground
·
Consider
pre-laying the toilet vent PVC pipe in the wall cavity so is not visible other
than outlet through roof
·
Make sure taps
are placed at correct spots on drawings
·
Check location of
downpipes
·
See my laundry
layout designs re location of WM & Dryer. Extended bench, overhead
cupboards,
·
Location of
outdoor taps
·
Check that venting
from exhaust fans toilets and bathrooms & kitchen rangehood goes outside,
not to roofs space.
Heating / Cooling:
·
Check the
location of ceiling vents for heating and cooling in bedrooms so they aren’t
directly above beds
·
Zoned heating
& evap cooling
·
heating duct to
laundry and ensuite upstairs
·
ability to set
timers
Kitchen:
·
Check size of
fridge area (Need greater than H178, W 91.5, D78)
·
Install fridge water
tap inside kitchen cupboards next to it (check not a draw)
·
Rangehood encased
in cupboards, streamlined look.
·
Rangehood vented
outside
·
Check cupboard and
bench top heights
·
Size of pot draws
·
Get adjustable
shelves in kitchen cupboards for different sized items with additional holes
for adjusting heights.
·
Depth of shelves
in WIP & overhead shelves minimum 30cm deep.
·
Cupboards on
island bench (bar stool side), also what is depth of gap under bench that side
·
Mitered edges,
waterfall benches in kitchen
·
Kitchen island
benchtop, check where joins will be placed. What max. cut? Confirm size.
·
Splashback join
locations, whats max. length of cut?
·
Size of window in
kitchen, largest possible in that splashback space. Centered.
·
Soft close
handless draws
Bathroom:
·
Bathrooms to have
floor to ceiling tiling
·
Check height of
tiling behind toilets
·
Partially Frosted
windows in bathrooms, cost?
·
Check which way
shower doors open and stipulate door opening direction in contract for all
doors (entry, pantry, wardrobes, shower, internal)
·
Upgrade shower
screens to Grange Series Overlap semi frameless. Master ensuite shower single
panel of glass.
·
Check location of
taps in shower
·
Vanitys, Do they
have draws or cupboards.
·
Extraction fans
vented to the outside
·
Towel rails and
toilet roll holders
·
Bathroom mirror –
how long it is, full length? Tiled behind it or plastered?
·
Sealing tiles -
Polished porcelain tiles and natural stone products may need to be sealed.
·
Ensuite sliding
cavity door
·
Floor to ceiling
tiles in all bathrooms; half wall tiles to powderrooms
·
Drainage waste
points in floor of bathrooms.
·
Guest ensuite
sliding door & WIR sliding door
·
How big is the window in the master bedroom ensuite? What is its height
from ground?
·
Will the bath tap in the master bedroom ensuite come from which wall or
have to be a floor mounted spout?
·
If floor mounted tap I want to know what tap you use as standard.
·
Also in the master ensuite upstairs the location of the towel bar is a
challenge, suggestions welcome.
·
Finally re the master ensuite, the size of shower is large. Instead of a
stegbar shower screen we want a frame-less panel of glass be used as screen
·
All bathroom basins to be Caroma Pearl 545 Inset Basins (Reece code
9503584) with Dorf Pearl Basin Mixer Chrome (Reece code, 2205964).
·
The upstairs toilet we need to discuss the size and location of the sink
as this area may indent into the bathroom as we want a cupboard & sink. I
would like the Caroma Pearl basin on a small wall hung cupboard, ie a small
version of bathroom, big enough that i can put a soap dispenser on it & in
single cupboard fit a spare toilet rolls etc. I have exact version sample
photos if you need. If I can't do this then can I suggest the White Stone Hox
Mini Basin (Reece code 9500530).
·
All baths to have MIZU push plug chrome.
·
Location of towel rails, toilet roll holders etc in bathrooms/toilets,
·
We want the MIZU drift toilet roll holders (but varies from left/right
depending on toilet). the MIZU drift Single towel bar chrome we'd like but need
to confirm length for each room based on where we can place them. Also the MIZU
drift robe hook chrome wanted in couple of places. And the MIZU drift Towel Rack
Chrome is wanted in the Guest bathroom downstairs above the bath.
·
Downstairs powder room, location of the sink and toilet need to be
swapped. This would create a better flow to the room and makes it safer for
less abled persons trying to access this room with frames etc. Also the indent
into WIP can be removed as fridge not going there hence creating more space in
WIP/toilet.
Bedroom:
·
Mirrored sliding
wardrobe doors
·
window in boys
room double horizontal window (see stegbar design or A&L )
·
windows check
type opening, air ventilation issues,
·
manhole in area
out of sight (WIR)
Laundry:
·
heating duct
·
Cavity Sliding
entry door
·
Space for dyer on
floor next to washing machine
·
Drainage waste
hole in laundry floor in case washing machine floods
·
Overhead
cupboards (see my plans)
·
Confirm what
cabinetry included.
·
Dimensions of
sink in prestige homes?
Living Areas:
·
Row of nogging to
hang pictures
·
Sliding doors x2
to be recessed into floor so no step over; if not on slab pour do a cut into
concrete.
·
Fireplace installed
with natural stone mantel piece and floor piece. See my pics/plans
o
Heat & Glo
6000 TRSI-AUD (rear vented) unit
o
TRIM 3 black, bevelled
o
Set half in and
half out. Therefore has to have stone mantle & base (as per display)
Alfresco / Patio
·
Check material
used for ceiling roof in alfresco is for outdoors
Driveway/Garage:
·
height of garage
door >1.9m
·
garage internal
door, deadbolted
·
Check garage
external hebel & internal plastering